CAPM Certification Practice Test 9

© examsiri.com
Question : 43 of 50
 
Marks: +1, -0
Upon evaluation, a newly appointed project manager identifies that the XYZ project has many risks with high-risk impact scores, but has an overall low risk score. How is this possible?