Harley is the project manager of the GHY Project for his company. He’s working with the project team to develop a robust project plan for the project. Marek, one of the project team members, doesn’t understand why so much time is needed for the project plan and wants to get to work on the project more quickly. Harold should explain that the project plan is used for all except one of the following. Which one isn’t it used for?