Christina is the project manager of a project to create an online help manual for customers of a product her company sells. Samuel, a writer for the project, is taking considerably longer than what was planned to create the documentation. While Samuel’s work is excellent, if he continues to be late with the needed documentation, the project will be late. Which of the following is NOT an appropriate corrective action for this problem?