Question : 25 of 50
 
Marks: +1, -0
Albert is the project manager of her project and she wants to recognize team members that have contributed to the project work in a significant way each month. Albert decides that she’ll use award one team member the title of “Team Member of the Month.” This person will get to park in a reserved parking space and will receive one paid day off from the project. What is the danger in Albert’s plan for rewards and recognition?