Question : 40 of 50
 
Marks: +1, -0
You are a project manager of a project to install a new piece of manufacturing equipment. The union is concerned that the new equipment will reduce the number of jobs needed to complete the work. The project is currently stopped until management and the union have resolved the problem. What is the union in this scenario?