CAPM Certification Practice Test 6

© examsiri.com
Question : 3 of 50
 
Marks: +1, -0
You are the project manager of the BHN Project. This project is expected to last four years and has a budget of 2.5 million dollars. Toni, one of your project team members, is responsible for documenting the technical aspects of the product. Toni, however, has been consistently late with his assignments. You have been very busy with other assignments and the rest of the project is going well in this early stage so you choose to not address the problem at this point. Which one of the following describes the conflict resolution method you are using?