CAPM Certification Practice Test 6

© examsiri.com
Question : 22 of 50
 
Marks: +1, -0
You are a project manager of a project to install new web software for your organization. The software project has been halted, however, due to a pending law that may change how the public can interact and use the information the software will provide. Until the legal situation is resolved, this project cannot move forward. The legal issue in this scenario is what?
Go to Question: