Question : 33 of 50
Marks:
+1,
-0
You are the project manager for your organization and you’re working with your project team to help coach them on the processes within project management. During this coaching you explain the difference between constraints and assumptions and how this affects project initiation. You also explain how long-term projects and short-term projects may be measured differently during project ignition. In light of this conversion, customer demands, changes to the marketplace, and opportunity are all examples of which one of the following?