Question : 22 of 50
Marks:
+1,
-0
You are a project manager responsible for the implementation of a software program. Your project team will travel to several hundred remote locations to install the software onsite. Project team members are reporting that the stakeholders in the locations are asking them to do extra configuration work as part of the install. If the changes are routed through the change control system, it may be several days before the changes can happen, and the project team members are only onsite for two days at each location. What should you do?
Go to Question: