CAPM Certification Practice Test 4

© examsiri.com
Question : 36 of 50
 
Marks: +1, -0
You are the project manager of the NHB Project. You’ve just learned that the cost of materials will increase by ten percent due to a hurricane in the Gulf Coast. You would like to update the cost baseline to reflect these unanticipated changes. Which one of the following is the best component to manage these cost changes?
Go to Question: