Question : 21 of 50
 
Marks: +1, -0
A project was estimated to cost $1.5M and scheduled to last 6 months. After three months, the earned value analysis shows the following - EV = $650,000, PV = $750,000, AC = $800,000. What is the Schedule Variance?