CAPM Certification Practice Test 4
© examsiri.com
Question : 12 of 50
Marks:
+1,
-0
Your project is not costing as much as you predicted. If you do not use your entire budget allotment for the first phase of the project, you will receive a budget reduction for the second phase of your project. You elect to order slightly better materials that will provide a higher product for the customer, but that will also allow you to meet the predicted budget for this phase of the project. This condition is best described as which one of the following?