CAPM Certification Practice Test 3

© examsiri.com
Question : 25 of 50
 
Marks: +1, -0
You are the project manager for your organization and are building the project team. One of the candidates you’re interviewing assures you that he’d be a great fit for the project team. In addition, the candidate informs you that he’d be happy to surrender half of his project bonus directly to you if you’d hire him. What is the best course of action in this instance?