Question : 45 of 50
Marks:
+1,
-0
You are the project manager of the HGF Project. The project scope has been approved by all stakeholders and management. The project is now moving forward. A week later, however, two of the key stakeholders, John and Tina, come to you demanding to change some aspects of the scope statement. What should the project manager do?