CAPM Certification Practice Test 1

© examsiri.com
Question : 23 of 50
 
Marks: +1, -0
You are the project manager of the MHG Project. This project has a budget of $350,000 and is scheduled to last ten months. Marcy, a key stakeholder of the project, is in disagreement with Tony, another key stakeholder on the expected levels of quality. She claims Tony’s accepted level of quality for the project is too high. Your project plan calls for the same metric that Tony is referring to as this is based on the company’s quality policy. Marcy says she will refuse to approve the project because of the cost of quality. What should you do?
Go to Question: