Question : 55 of 100
Marks:
+1,
-0
A contractor undertook a contract for a construction work to be completed in 180 days. He engaged 120 labours. But only 1/6th of the work was done in 1/5th of the scheduled time. The additional number of labours that will be required to complete the work in time, is